GUAJIRO SOLAR PV PLANT

Design, engineering, procurement, construction, testing, and commissioning of the “Guajiro” solar photovoltaic plant, with an installed capacity of 101.40 MW. The scope includes the complete execution of all works required for the project, from site preparation through the installation of electrical and interconnection infrastructure, as well as the construction of operation and maintenance buildings, control […]
CONSTRUCTION AND FIT-OUT OF CORPORATE INTERIORS AND OFFICE FLOORS FOR MAPFRE MEXICO HEADQUARTERS

The project involved the comprehensive execution of interior finishes, building services, and technical furnishings for Mapfre’s new offices on Avenida Revolución in Mexico City, under a fixed-price contract. Works were carried out across all floors of the building, from the basement through Level 9, including lighting, HVAC systems, partitions and glazing, civil works, and ancillary […]
MORELOS HIGH-PRESSURE GAS PIPELINE

Construction of the “Morelos” high-pressure gas pipeline, comprising 160 km of 30″ and 24″ steel pipelines, including civil works, mechanical works, special crossings, and valve stations. The project encompasses the complete construction of the gas pipeline in two sections: Cuautla–Atlixco and Atlixco–Tlaxcala, crossing the states of Morelos, Puebla, and Tlaxcala. The scope of work includes […]
LOS DIABLOS SPORTS FACILITY

Comprehensive construction of a professional baseball stadium for the Diablos Rojos del México team. The project included the construction of covered stands, VIP areas, service facilities, changing rooms, offices, access areas, technical facilities, and external urban development works. The stadium was designed to meet international standards and provide a modern, high-quality sporting experience. The project […]
TÚNEL EMISOR PONIENTE II

TÚNEL EMISOR PONIENTE IIConstruction of the first stage of the Túnel Emisor Poniente II and improvement of the open-channel section of the existing Emisor Poniente.The works included the initial construction of the Túnel Emisor Poniente II, comprising excavation, lining, and ventilation systems, as well as the rectification and adaptation of the existing open-channel section.The project […]
GUERRERO NEGRO IV

Execution of works for the supply and installation of equipment at the Guerrero Negro desalination plant in Baja California Sur. The works included the installation of mechanical, hydraulic, and electrical systems, as well as the adaptation of existing infrastructure to optimise the production and distribution of drinking water. The scope also included commissioning and operational […]
EXTENSION OF LINE 12 OF THE MEXICO CITY METRO SYSTEM

Ampliación de la Línea 12 del Sistema de Transporte Colectivo Metro de Ciudad de México, consistente en la ejecución de 3,5 km de túnel excavado mediante medios mecánicos, empleando rozadora y sin uso de explosivos. El proyecto incluye la construcción de dos estaciones subterráneas —Álvaro Obregón y Valentín Campa—, así como lumbreras estratégicas para ventilación […]
GESTAMP SAN LUIS

Design and construction of an industrial plant dedicated to the manufacture of automotive components under a turnkey contract. The project included the construction of steel structures, foundations, external cladding, civil works, finishes, and complementary installations, all carried out in accordance with strict quality standards. The project was executed in two successive phases.
CONSTRUCTION OF MACHINE ROOMS, EQUIPMENT AND ELECTROMECHANICAL INSTALLATIONS FOR THE DURANGO–MAZATLÁN HIGHWAY TUNNELS

Comprehensive construction of machine rooms, utility connections, ventilation, lighting, safety, communications, and centralised control systems for the tunnels along the Durango–Mazatlán Highway, including civil works, electromechanical installations, and associated works. The scope included the manufacture and installation of forced ventilation systems, interior and exterior lighting, electronic safety systems, communications and traffic control systems, as well […]
2121 POLANCO SMART METERS

Execution of the works required for the removal, supply, and installation of AMI-type smart meters compatible with various communication technologies in Mexico City. The scope includes the replacement of existing equipment, installation of new metering devices at strategic locations, configuration and calibration of each unit, and integration of the systems with the control centre to […]