KAWICE FUEL TERMINAL STORAGE TANK

The project consists of the construction of a 33,000 m³ fuel storage tank at the Kawice Fuel Terminal, located in the Lower Silesian Voivodeship. The scope of the contract also includes all the auxiliary infrastructure required to integrate the new tank into the terminal’s existing systems. The project will be carried out for PERN, Poland’s […]
CHOCZEWO – GDAŃSK PRZYJAŹŃ ELECTRICITY TRANSMISSION LINE

Construction of the 400 kV Choczewo – Gdańsk Przyjaźń electricity transmission line in northern Poland. The complete line will have a total length of 90 km, crossing 10 municipalities in the Pomerania region and connecting the Choczewo substation with the Gdańsk Przyjaźń substation. Specifically, this new transmission line will facilitate the integration of electricity generated […]
NAMYSŁÓW–OLEŚNICA ELECTRICITY TRANSMISSION LINE

The project signed with Polskie Sieci Elektroenergetyczne (PSE) involves the construction of a 40-km electricity transmission line running from Namysłów County, in the Opole Voivodeship, through the municipalities of Wilków and Namysłów, to Oleśnica County, in the Lower Silesian Voivodeship. The project will be carried out in southern Poland, while the other three projects signed […]
BOBROWNIKI–SKÓROWO SECTION OF THE S6 EXPRESSWAY

Construction of the Bobrowniki–Skórowo section of the S6 expressway, a nearly 13-kilometre stretch that opened to traffic on 26 June 2026 and helps improve road connectivity between Szczecin and the Gdańsk metropolitan area. The project included the construction of the Rzechcino and Skórowo interchanges, engineering structures, drainage systems, noise barriers, wildlife crossings and fencing. One […]
CONNECTION OF THE CHOCZEWO SUBSTATION TO THE SŁUPSK–ŻARNOWIEC TRANSMISSION LINE

The project consists of connecting the Choczewo substation to the existing Słupsk–Żarnowiec transmission line, with the aim of strengthening Poland’s power grid and facilitating the integration of electricity generated by offshore wind farms in the Baltic Sea. Aldesa is constructing this 400 kV transmission line for Poland’s transmission system operator, Polskie Sieci Elektroenergetyczne (PSE).
CHOCZEWO – GDAŃSK BŁONIA – GRUDZIĄDZ WĘGROWO POWER TRANSMISSION LINE

The project aims to strengthen Poland’s power grid and facilitate the integration of electricity generated by offshore wind farms in the Baltic Sea through the construction of a 400 kV transmission line along the Choczewo – Gdańsk Błonia – Grudziądz Węgrowo route. With this project, Poland’s transmission system operator, Polskie Sieci Elektroenergetyczne (PSE), once again […]
FUEL OIL STORAGE TANK – KOLUSZKI

Construction of a fuel oil storage tank in Koluszki with a capacity of 33,000 cubic metres, together with the associated infrastructure. The project will increase the facility’s total storage capacity from 439,000 to 472,000 cubic metres. This expansion will help improve the operational efficiency of the complex and strengthen the fuel logistics network in the […]
Reconstrucción y ampliación de la carretera regional n.º 877: Dylągówka – Szklary

Aldesa Polska is carrying out the reconstruction and expansion project of Regional Road No. 877 on the Dylągówka – Szklary section. The total investment value amounts to PLN 143,753,607.00. As part of the project, the following sections will be constructed: from approximately km 63+816, at the junction of Regional Road DW 877 and DW 878, […]
Design and Construction of Regional Road No. 213 to the Łęczyce Interchange on the S6 Expressway

Aldesa Polska, commissioned by the General Directorate for National Roads and Motorways – Gdańsk Branch, is carrying out a project to build a new section of national road leading to the planned Lubiatowo-Kopalino Nuclear Power Plant. The investment is a key element of the road infrastructure, ensuring efficient connectivity between the power plant site and […]
Construction of the S6 Expressway: Bobrowniki – Skórowo

The contract covers the construction of a dual-carriageway expressway on the 13-kilometre section between the Bobrowniki and Skórowo interchanges, as well as the construction of two road interchanges – Rzechcino and Skórowo – together with the associated infrastructure. The contract value amounts to PLN 283.1 million. This is one of three sections of the Słupsk […]