Infrastructure

Modernisation of the Gdańsk Stogi Tram Line

CLIENT

Client not available

Localization

POLAND

Activity

Railways

The project involved the reconstruction of approximately 4 km of double-track tram line, divided into three sections:

Budzysza Street, from the junction with Sucharskiego Street to the junction with Skiby Street.

Stryjewskiego Street, from the junction with Skiby Street to the junction of Nowotna Street and Krucza Street, including the “Pasanil” tram loop.

Nowotna Street, from Krucza Street to the “Stogi Plaża” tram loop.

As part of the investment, the road layout was also reconstructed, including pavements, access roads, and pedestrian and cycle routes. Two tram loops were built, 14 new tram stops were installed along the route, and 17 Strail-type level crossings were constructed.

Execution time

Duration not specified

Budget

-

Status