Aldesa Polska, commissioned by the General Directorate for National Roads and Motorways – Gdańsk Branch, is carrying out a project to build a new section of national road leading to the planned Lubiatowo-Kopalino Nuclear Power Plant. The investment is a key element of the road infrastructure, ensuring efficient connectivity between the power plant site and the S6 expressway.
The scope includes the design and construction of approximately 15 km of a GP-class road (1×2) from Regional Road No. 213 to the Łęczyce interchange on the S6 expressway, together with the construction of a connecting road to the county road in Łęczyce. The project is being delivered under the “Design and Build” formula, covering the preparation of design documentation, obtaining the ZRID road investment permit, and carrying out the construction works.
The contract value is nearly PLN 200 million gross. Completion is scheduled for the second quarter of 2029.