Infrastructure

BOBROWNIKI–SKÓROWO SECTION OF THE S6 EXPRESSWAY

CLIENT

Dirección General de Carreteras Nacionales y Autopistas de Polonia (GDDKiA)

Localization

POLAND

Activity

Roads

Construction of the Bobrowniki–Skórowo section of the S6 expressway, a nearly 13-kilometre stretch that opened to traffic on 26 June 2026 and helps improve road connectivity between Szczecin and the Gdańsk metropolitan area. The project included the construction of the Rzechcino and Skórowo interchanges, engineering structures, drainage systems, noise barriers, wildlife crossings and fencing. One of the project’s main technical features is the use of concrete pavement, a solution that is still relatively uncommon on Polish expressways and was selected for its durability.

Execution time

Duration not specified

Budget

€66,000,000.00

Status

Completed